Betan Karnali PRoR Hydro-electric Project
- Project Date:23 November 2017
- Our Team:
- Client:
- Categories:Detailed Engineering Study
Description
BETAN KARNALI PRoR HYDROELECTRIC PROJECT (688 MW)
Commencement |
December 23,2017 |
Proposed Completion |
October 5 ,2019 |
Duration |
18 + 3.5 Months |
Quick View of the Project (Based on desk study)
Generals |
||
|
The Employer |
Betan Karnali Sanchayakarta Hydropower Company Ltd. Pulchowk, Lalitpur Nepal |
|
The Consultant |
NEA Engineering Company Limited |
|
Project Location |
Border of Achham District and Surkhet District |
|
|
Latitudes 28°56’ 04” to 28°50’57” |
|
|
Longitudes 81°24’ 42” to 81°11’ 43” |
|
Accessibility |
Upto Bijaura – accessible by Motor vehicle. Powerhouse arounf 80 KM via road from Birendranagar, Surkhet along Baddichaur, Babiya Chaur, Guttu and Bijaura road. |
|
Access Road to Project Area |
22 km from Bajura in Design Phase |
Technical |
||
|
Project Type |
Peaking Run-of-River |
Hydrology and Sediment Study |
||
|
Karnali River |
|
Catchment Area |
:22,511.25 Km2 |
|
Annual Mean Flow |
554.13 m3/s |
|
Maximum Monthly Discharge |
1609.49 m3/s |
|
Minimum Monthly Discharge |
134.61 m3/s |
|
Wet Design Discharge (Q) |
580 m3/s |
|
Dam |
||
Type of Dam |
Roller compacted Concrete ( RCC) |
|
Elevation of Dam Location |
478.00 masl Approx. 2.0 Km D/S from Malbela |
|
Dam Height |
89m from Riverbed |
|
Water Conveyance System |
||
Headrace tunnel |
|
|
Number |
3 nos |
|
Size and shape |
8 m diameter and circular |
|
Length | 2481 m each | |
Lining | 400 mm thick Concrete Circular lining | |
Maximum Velocity | 3.85m/s | |
Surge Shaft/Tunnel | ||
Type | Restricted Orifice | |
Number | 3 nos | |
Height | 60 m | |
Diameter | 25 m circular | |
Pressure Shaft | ||
Number | 3 nos | |
Diameter | 7 m diameter circular | |
Length | 298 m each | |
penstock Bifurcation | from each penstock 2 nos of bifurcation | |
Penstock |
||
Length |
: 345 m (Approx.) |
|
Type |
: Tunnel |
|
|
Powerhouse |
|
Coordinate | 81°14'48" E, 28°55'5”N | |
Type |
Surface+Dam Toe for environmental release |
|
Installed capacity | 434+8 MW | |
PowerHouse Size | 150m X 20m X 40 m ( L X B X H) | |
Number and capacity of units |
6 nos x 72.33 MW +2 nos. x 4 MW |
|
Type of Turbine |
: Francis,vertical axis |
|
Normal trial water level |
374 masl |
|
Gross Head | 99.3 m | |
Rated Net Head | 94.3 m | |
Tailrace Tunnel/Channel |
||
Number |
6 nos of tunnel leading to channel |
|
Size and shape | Trapezoidal Channel | |
Length | 153m length each tunnel leading to 105m | |
Lining | concrete lining | |
Energy |
||
Wet Season Energy | 1623 GWh/yr | |
Dry Season peak Energy |
411GWh/yr |
|
Dry Season off peak energy |
284 GWh/yr |
|
Dry Season Total energy |
695 GWh/yr |
|
Total annual energy |
2318GWH/yr |
Consultant Scope of Works:
- Literature review of the previous study;
Detailed Engineering study of BKHEP incorporating the technical, financial, Socio-economic and relevant aspects of the project development based on detailed survey and investigations.