Client: Vidhyut Utpadan Company Limited (VUCL)
Contract Effective Date: October 21, 2021
Contract Amount: NPR 13,98,106.04
Project Location: Sanni Tribeni Rural Municipality and Khandachakra Municipality of Kalikot district, Karnali Province
Project Description: This project aims to carry out Initial Environmental Examination (IEE) of nearly 2.2 kilometers long 400
kv double circuit transmission line proposed to evacuate power produced from Phukot Karnali PROR Hydroelectric project
to proposed Phukot sub-station at Rengil (Khandachakra Municipality – 11). Scope of the project includes the preparation
and approval of Terms of Reference (ToR) for IEE study and preparation and approval of IEE report as per the provisions of
Environment Protection Regulations, 2077. Final IEE report of the project has been approved by MoEWRI on 2081/5/27.
Status Completed
Tags: Environment Study